Population:
119.204
GDP per capita:
13.630,00 EUR
Unemployment rate:
4,70%
Average Gross Salary:
1.730,00 EUR
Average Net Salary:
1.276,00 EUR
Road:
0,1 km
Highway:
A2, 1 km
Railway siding:
0 km
Sea port:
Rijeka, 190 km
Airport:
Zagreb International Airport – Franjo Tuđman, 50 km
| Location (city/municipality) | Zabok |
|---|---|
| Zone type | Business zone |
| Area of the zone (m²) | 1.913.600 |
| Available land (m²) | 871.371 |
| Land use | Manufacturing and services |
| Building coverage ratio | 0,6 |
| Floor area ratio | 1,0 |
| Allowed construction height (m) | 15/20 |
| Allowed noise level (at the border of the site, dB) | 65/50 |
| Gas | |
|---|---|
| Availability | Yes |
| Electricity | |
| Availability | Yes |
| Water | |
| Availability | Yes |
| Sewage | |
| Availability | Yes |
| Water purifier | No |
| Communal contribution fee | |
|---|---|
| Communal contribution for manufacturing (EUR/m³) | 1,33 |
| Communal contribution for office spaces (EUR/m³) | 2,65 |
| Communal contribution for services (EUR/m³) | 2,65 |
| Redemption from paying communal contribution fee | Yes, exemption from paying the communal contribution of 50% for the construction of production facilities. |
| Communal contribution tax | |
| Amount of communal contribution tax (EUR/m²) | 1,27-12,70 |
| Redemption from paying communal contribution tax | Yes, exemption from paying utility fees for newly built buildings 100% in the first year, 50% in the second year and 25% in the third year. For business premises and construction land used for business activities, when business activities are not carried out for more than six months in a calendar year, the use coefficient is reduced by 50%, but cannot be lower than the use coefficient for residential premises or undeveloped construction land. Also, the obligation to pay utility fees will be exempted from paying utility fees for business premises, whose premises have been significantly damaged due to force majeure (fire, flood, earthquake, etc.), in the amount of 80%. |
| Water fee | |
| Water regulation fee (EUR/m²) | 0,04-0,14 |
| County urban plan | Yes |
| Municipal/City urban plan | Yes |
| Urban development plan | No obligation |
| Detailed urban plan | No obligation |
Ministry of Economy assumes no legal responsibility for the accuracy or comprehensiveness of the data supplied in this database. Ministry of Economy accepts no liability for any direct, indirect, consequential or incidental damages or losses arising from use of the data collection.